Parcel JK is a 430,000 square-foot, 9-story science and technology building with ground floor retail that is being constructed as a ground-up core and shell structure. CX is currently seeking out and reviewing potential tenants for this state-of-the-art building. 



Winter 2017 - 2018

  • Concrete pours of the mat slab foundation complete.
  • Structural steel will begin to be erected from the bottom level, up to the top level. 


Spring 2018

  • MEP’s (mechanical, electrical, and plumbing) and elevators will begin to be installed.
  • Exterior walls will begin to be installed, followed by the roofing system
  • Interior finishes will begin.

Construction update - week of December 10, 2018

Please refer to the map to identify the areas outlined in the update below.

Building JK –

  • Exterior glass installation is progressing around the building.
  • Interior mechanical, electrical, and plumbing work continues.

Site EF –

  • Sheeting operations for parcel EF is complete.

Lot G –

  • Sheeting piling is ongoing.

Site Work –

  • Utilities are substantially complete. Final road paving will continue. (1)

Pump Station - 

  • Ground compaction is taking place this month. Once this is complete, utility work will continue. (2)

Cambridge Crossing Common –

  • Work will continue in various areas throughout the Commons. Temporary fencing and pedestrian restrictions will be in place on the East end of the Common, but the park will remain open. (3)

MOB Highway -

  • McCourt will continue to install utilities near the MBTA bus terminal. Lanes will be shifted during this work. A police detail will be on site to assist with traffic flow.

*Please note –

  • The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing.

Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971