Parcel JK is a 430,000 square-foot, 9-story science and technology building with ground floor retail that is being constructed as a ground-up core and shell structure. CX is currently seeking out and reviewing potential tenants for this state-of-the-art building. 



Winter 2017 - 2018

  • Concrete pours of the mat slab foundation complete.
  • Structural steel will begin to be erected from the bottom level, up to the top level. 


Spring 2018

  • MEP’s (mechanical, electrical, and plumbing) and elevators will begin to be installed.
  • Exterior walls will begin to be installed, followed by the roofing system
  • Interior finishes will begin.

Construction update - week of October 22, 2018

Please refer to the map to identify the areas outlined in the update below.

   Building JK –

  • Exterior glass installation is progressing around the building.
  • Interior mechanical, electrical, and plumbing work continues.
  • Concrete floors are being placed weekly.
  • Please note – Concrete operations will continue, work may continue past 6:00 pm due to unforeseen conditions or concrete finishing needs. We do not anticipate this work to be disruptive.

Site EF –

  • Sheeting operations for parcel EF have been completed.


Site Work –

  • Utilities will continue to be installed within the project site. (1)


Pump Station -

  • Installation of surcharge material around the station area will be completed early this week. The top of the pump station has been installed. (3)

Cambridge Crossing Common –

  • Work will continue in various areas throughout the Commons. Temporary fencing and pedestrian restrictions will be in place on the East end of the Common, but the park will remain open. (2)


Water Street / MOB Highway  -

  • The sewer force main work on Water Street is complete. The work is now taking place in the median of Monsignor O’Brien Highway, heading towards Gore Street.

*Please note –

  • The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing.

Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971