Parcel JK is a 430,000 square-foot, 9-story science and technology building with ground floor retail that is being constructed as a ground-up core and shell structure. CX is currently seeking out and reviewing potential tenants for this state-of-the-art building. 



Winter 2019

  • Interior finishes will continue.
  • Interior MEP (mechanical, electrical, and plumbing) systems will be completed and commissioned. 
  • Exterior finishes, such as sidewalks, lighting, and seating will be installed.
  • The exterior facade will be completed.

Construction update - week of January 7, 2019

Building JK

  • Exterior glass installation is progressing around the building.
  • Interior mechanical, electrical, and plumbing work continues.
  • Interior core work and fit-outs will take place.

Site EF

  • Sheeting operations for parcel EF is complete. 

Lot G

  • Sheeting operations are ongoing.
  • Installation of 1st level bracing will begin. 

Site Work

  •  Site work is substantially complete. (1) 

Pump Station

  • Utility work is ongoing on West Boulevard. (2) 

Cambridge Crossing Common

  • Work is this area is currently on hold until the spring. (3) 

MOB Highway

  • McCourt will continue to install utilities near the MBTA bus terminal. Lanes will be shifted during this work. A police detail will be on site to assist with traffic flow. 

Please note

  • The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing. 

Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971