Gore Street Utility Project

The City of Cambridge and Divco West, developer of Cambridge Crossing, will be undertaking construction on Gore Street between Monsignor O’Brien Highway and Warren Street This construction is an opportunity to incorporate improvements into Gore Street; sidewalks, crosswalks, street trees improved access to the park, etc. 

construction update - Week of December 10, 2018

Crew 1 – The last water shut down work was completed, so the sewer main installation will continue to progress towards 7th Street.


Crew 2 – Sewer main installation work will continue to progress from 2nd Street towards 3rd Street.


General Sewer Main Construction

  • Work hours will be 7 AM to 4 PM, Monday through Friday, and Saturday 9 AM to 6 PM.
  • There will be noise and disruption from construction activities.
  • Depending on the work planned, flyers may also be distributed to impacted residents. 
  • “No Parking” signs will be posted; please be sure to check dates/times.
  • Roadway and driveway access will be maintained but may be restricted at times.
  • Pedestrian access and access into properties will be maintained at all times but may be restricted in certain ways.
  • Emergency vehicles will have access at all times and all city services will continue.

Gore Street Community Meeting Presentation

 Please click the link below to reference the presentation from the community meeting held on May 30th. 

Click Here

CONTACT MITIGATION

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971