Enhancements now under construction on the common include installation of seat walls, construction of pedestrian gathering areas, improvements to the community path, construction of railroad tie bridges and walkways, additional plantings and construction of reclaimed granite outcropping area, among other enhancements. Enhanced Common to open Summer 2019.

Construction Update -

CX Commons

Work is currently on hold until the spring of 2019. At that time, work will resume for the landscaping and plantings. 


The work on the Common will take place in more areas outside of the West End.

  • The picnic areas will be constructed this year.
  • Fences will be moved further inward towards the main Common Area as well as a portion towards Child Street.
  • Once the fences have been relocated, excavation activity will commence.
  • There are multiple phases planned for this years’ operations that will require different fence configurations.  
  • Construction activities and access will occur within the construction sites.
  • As work areas are complete, more areas of the Common will be opened to the public.
  • Please note, click on the image to enlarge.



image31

CONTACT MITIGATION

 