CX │ CONSTRUCTION UPDATES

1/4

Additional Photos

More site photos can be found here.

Construction update - week of May 23, 2022

Parcel V (former Lechmere Station)

  • Pedestrian routes are shifting as the walkways and tunnel close at the site. Pedestrians will be directed to the north side of Monsignor O’Brien Highway and to the south side of      Cambridge Street via Second or East streets to avoid site construction activities. 
  • Fencing and gates continue to be installed around the site.
  • General site cleanup of MBTA material is underway.
  • Demolition of the former MBTA subway track, viaduct abutment will begin with soil excavation.  

250 Water Street (Parcel EF)

  • Exterior framing will continue.
  • Insulation will continue to be installed.
  • Punch-list work will take place in the garage slab area.
  • Installation of loading dock rails will occur.
  • Fireproofing and framing will occur on Level 1 and Level 3.
  • Installation of metal panels and glass will take place.
  • Boarding of ceilings and preparation for floors work will occur.
  • Heating units will be installed.
  • Electrical, tele-data, and security networks will be installed.

350 Water Street (Parcel G)

  • Façade installation will continue at podium levels.
  • Interior fit-out work is ongoing.
  • Exterior sitework and landscaping work will continue at the Southeast corner.
  • Activities will take place on Saturday, May 21st starting at 9:00 AM.

151 North First Street (Parcel I)

  • General deliveries will take place through the gate on the corner of Morgan Ave and North First Street.
  • Interior fit-out work is ongoing.
  • Exterior sitework and landscaping will continue on all elevations.  
  • Activities will take place on Saturday, May 21st starting at 9:00 AM.

450 Water Street (Parcel H)

  • Landscaping activities on the east and south side of the site are ongoing

441 Morgan Ave (Parcel U)

  • The site fence has been moved into Leighton Street and the roadway is now switched to one lane towards MOB moving forward. Morgan Ave is two way but with no parking and no sidewalk access in front of the site. Pedestrians should follow wayfinding signage to access the sidewalk on the north side of Morgan Ave, closest to the Common.  
  • Utility monitoring points will be surveyed weekly with the project team set up on the sidewalk and in the street on Morgan Ave and Leighton Street.
  • Bracing will continue to be removed.
  • Clips continue to be installed in preparation for structural steel.
  • Structural steel will continue to be installed.
  • A tower crane has been installed on site and will remain on site for the majority of the project’s exterior work. The crane is designed to move or “weathervane” in the wind.  It will not be operating during high wind events.
  • Activities will take place on Saturday, May 21st with noise generating activities starting at 9:00 AM.

181 Morgan Ave (Parcel Q1)

  •  Punch-list on the exterior and interior will continue. 

Dog Park (in front of Twenty / 20) -

  • Activities at the dog park are complete and punch-list work is ongoing.

General Site Work –

  • Soil, test pit and boring work will be underway this spring at Water Street and Morgan Avenue near the MBTA bus area.

Please refer to the map below

Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 475-5198 