Construction update - week of July 22, 2019

Building JK (1)

  • Exterior glass installation is progressing around the building.
  • Interior mechanical, electrical, and plumbing work continues.
  • Interior core work and fit-outs will take place.
  • Installation of curbing and landscaping activities will continue.

Site EF (2)

  • Beams will be installed to support construction at the upper level.

Site G (3)

  • Excavation will continue as bracing is installed. 
  • Installation of stone and drainage is ongoing.
  • Concrete pours will take place.
  • Installation of mat reinforcement will begin.

Site I (4)

  •  Removal of surcharge material will take place. 

Site H (5)

  • Excavation and off site hauling of materials will continue this week.
  • Internal bracing of the sheeting continues.
  • Mock-up work is ongoing.
  • The concrete subcontractor will continue placing pile caps in the south east.

Site W (6)

  • Work will continue to take place within the site fence.

Site Q1 (7)

  • Pre-excavation activities and site utility work will take place.

Site Work (8)

  •  Site work is substantially complete.  

Cambridge Crossing Common (9)

  • Landscaping activities will continue to take place.
  • Installation of stone will continue for the landforms. 
  • Soils will be placed in various locations dependent on dry weather.
  • Outfall reconstruction is ongoing.
  • Soil removal, replacement, and re-grading will take place in the  

Pump Station (10)

  • Installation of under slab utilities is underway.
  • The site will be brought up to grade as backfilling activities continue. 

*Please note

The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing.  

CX Commons

image1

the future of the commons

CX Commons

Work is just picked back up after being on hold for the winter months. Current activities include landscaping and plantings. 


The work on the Common will take place in more areas outside of the West End.

  • The picnic areas will be constructed this year.
  • Fences will be moved further inward towards the main Common Area as well as a portion towards Child Street.
  • Once the fences have been relocated, excavation activity will commence.
  • There are multiple phases planned for this years’ operations that will require different fence configurations.  
  • Construction activities and access will occur within the construction sites.
  • As work areas are complete, more areas of the Common will be opened to the public.


Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971