Punchlist activities will continue throughout the site.
Fit-outs are ongoing and are in the final stages of construction.
Site EF
Sequences will continue to be erected.
Deck detailing and installation of studs continues.
Forming and pouring of crane tie pedestals is ongoing.
Mesh, rebar, and MEP (mechanical, electrical, and plumbing) installations will continue.
SOD will continue to be poured.
Stairs will continue to be installed.
Curb and column encasements will take place.
Site G
Dismantling of a tower crane will take place on Saturday, February 27th and continuing through Sunday, February 28th. Work hours for each day will be 5:00 AM - 9:00 PM.
MEP (mechanical, electrical, and plumbing) fireproofing will be installed throughout the building.
Pre-cast installation activities are substantially complete.
Façade installation will continue at podium levels.
Mechanical equipment will be hoisted to the roof.
Site I
Steel deliveries will take place during the mornings.
Steel erection in the parking garage is ongoing.
Parking garage walls are progressing.
Utility infrastructure work in the park is ongoing.
Sewer installation will take place in Water Street between Parcel I and Parcel Q.
Site H
Major king pile installations will take place at the north end wall, which is expected to create some noise.
Utility work will continue on the West Road between Parcel G and Parcel H.
Masonry work continues at the loading dock and lobby for the CMU walls.
Curtainwall installation is ongoing.
Installation of spray fireproofing and MEP (mechanical, electrical, and plumbing) fit-outs are ongoing throughout the building.
Delivery and installation of fit out equipment will take place from Tuesday, March 2nd to Friday, March 5th via a crane at the north end of the west roadway.
Installation of curtainwall for the lobby will take place starting Thursday, March 4th via the south end of the west roadway.
Site U
Test pits will be finishing up on Morgan Avenue.
Trenching will take place inside the fence line for installation of conduit.
Site Q1 (6)
Punch-list on the exterior and interior will continue.
MBTA Station Plaza (7)
Scope of work has been completed in this area for the time being.
Monsignor O’Brien Highway
Excavation activities will take place for installation of traffic conduit.
Excavation and removal of elevated concrete footings will take place.
Lechmere Canal
Work is complete until the Spring.
*Please note
The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing.