Construction update - week of October 14, 2019

Building JK (1)

  • Interior core work is complete, and interior tenant fit-outs will continue to take place.   
  • Installation of curbing and landscaping activities will continue.    

Site EF (2)

  • Bracing beams will be installed to support construction at the upper levels of the foundations. 
  • Excavation activities and hauling of materials off-site is ongoing.

Site G (3)

  • The removal of lower level support of excavation will continue.
  • Construction of the foundation wall will continue.

Site I (4)

  • Removal of surcharge material will continue.
  • Pre-trenching activities will take place.
  • Sheeting will begin to be delivered to the site, in preparation for sheet piling in early November.

Site H (5)

  • Excavation and off site hauling of materials continues.
  • Internal bracing of the sheeting will take place.  
  • Placement of the pile caps in the North East side of the site is ongoing.  
  • The tower crane will begin to be erected the week of October 14th.    

Site W (6)

  • Work will continue to take place within the site fence.

Site Q1 (7)

  •  Pre-excavation activities including site utilities will continue. 

Cambridge Crossing Common (8)

  • Landscaping activities will continue to take place.
  • Installation of stone will continue for the landforms. 
  • Outfall reconstruction is ongoing.
  • Soil removal, replacement, and re-grading will take place.

Pump Station (9)

  • Installation of under slab utilities is underway.
  • Concrete placements will occur this week.
  • The site will be brought up to grade as backfilling activities continue. 

*Please note

  • The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing. 

CX Commons

image1

the future of the commons

CX Commons

Work is just picked back up after being on hold for the winter months. Current activities include landscaping and plantings. 


The work on the Common will take place in more areas outside of the West End.

  • The picnic areas will be constructed this year.
  • Fences will be moved further inward towards the main Common Area as well as a portion towards Child Street.
  • Once the fences have been relocated, excavation activity will commence.
  • There are multiple phases planned for this years’ operations that will require different fence configurations.  
  • Construction activities and access will occur within the construction sites.
  • As work areas are complete, more areas of the Common will be opened to the public.


Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971