• Home
  • CX Construction
  • Utility Projects
  • Events & News
    • Home
    • CX Construction
    • Utility Projects
    • Events & News
  • Home
  • CX Construction
  • Utility Projects
  • Events & News

CX │ CONSTRUCTION UPDATES

Additional Photos

More site photos can be found here.

Construction update - week of January 18, 2021

Building JK (1)

  • Façade and MEP (mechanical, electrical, and plumbing) installations will take place on Monday, January 18th starting at 9:00AM.
  • Punchlist activities will be ongoing at the base building.
  • Fit-outs are ongoing and are in the final stages of construction.
  • Testing and inspections will be upcoming once work is complete.

Site EF (2)

  • Sequences will be erected by the tower cranes.
  • Deck detailing and installation of studs will take place.
  • Forming and pouring of crane tie pedestals is ongoing.
  • Mesh, rebar, and MEP (mechanical, electrical, and plumbing) installations will continue.
  • SOD will continue to be poured.
  • Stairs will continue to be installed.
  • Curb and column encasements will take place.

Site G (3)

  • Erection of steel is complete.
  • MEP (mechanical, electrical, and plumbing) fireproofing will be installed throughout the building.
  • Pre-cast installation activities are substantially complete.
  • Façade installation will continue at podium levels.
  • Mechanical equipment will be hoisted to the roof.

Site I (4)

  • Steel deliveries will take place during the morning on Monday, January 18th.
  • Steel erection in the parking garage will begin this week.
  • Parking garage walls are progressing.
  • Utility infrastructure work in the park is ongoing.
  • Sewer installation will take place in Water Street between Parcel I and Parcel Q.

Site H (5)

  • Major “King Pile” installations will take place at the north end wall, which is expected to create some noise.
  • Utility work will continue on the West Road between Parcel G and Parcel H.
  • Masonry work continues at the loading dock and lobby for the CMU walls.
  • Placing and forming of slabs on metal decking will continue.
  • Curtainwall installation is ongoing.
  • Installation of spray fireproofing and MEP (mechanical, electrical, and plumbing) fit-outs are ongoing throughout the building.

Site Q1 (6)

  •  Punch-list on the exterior and interior will continue. 

MBTA Station Plaza (7)

  • Excavation and installation of granite curbing will be installed.

Monsignor O’Brien Highway

  • Excavation activities and installation of a water line will take place.

Lechmere Canal

  • Preparations for landscaping are ongoing.

*Please note

  • The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing. 

Please refer to the map below

Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971

Copyright © 2019 Cambridge Crossing Construction - All Rights Reserved