Construction update - week of August 26, 2019

Building JK (1)

  • Interior core work is complete, and interior tenant fit-outs will continue to take place.   
  • Installation of curbing and landscaping activities will continue.    

Site EF (2)

  • Bracing beams will be installed to support construction at the upper levels of the foundations. 
  • Excavation activities and hauling of materials off-site is ongoing.

Site G (3)

  • The final concrete pour is scheduled for Saturday, September 7th. Work will take place from 12:00 AM and will continue until 9:00 PM. The concrete pump trucks will be set up on site on the Friday before each pour to minimize noise impacts to abutters. Installation of mat reinforcement will continue.

Site I (4)

  •  Removal of surcharge material will take place. 

Site H (5)

  • Excavation and off site hauling of materials continues.
  • Internal bracing of the sheeting will take place.
  • The concrete pile caps at the south east corner will continue.

Site W (6)

  • Work will continue to take place within the site fence.

Site Q1 (7)

  •  Pre-excavation activities including site utilities will continue. 

Cambridge Crossing Common (8)

  • Landscaping activities will continue to take place.
  • Installation of stone will continue for the landforms. 
  • Outfall reconstruction is ongoing.
  • Soil removal, replacement, and re-grading will take place.

Pump Station (9)

  • Installation of under slab utilities is underway.
  • Concrete placements will occur this week.
  • The site will be brought up to grade as backfilling activities continue. 

*Please note

  • The GLX green line project has mobilized to the site. The Divco project teams are coordinating with them regularly but their work is independent from Cambridge Crossing. 

CX Commons

image1

the future of the commons

CX Commons

Work is just picked back up after being on hold for the winter months. Current activities include landscaping and plantings. 


The work on the Common will take place in more areas outside of the West End.

  • The picnic areas will be constructed this year.
  • Fences will be moved further inward towards the main Common Area as well as a portion towards Child Street.
  • Once the fences have been relocated, excavation activity will commence.
  • There are multiple phases planned for this years’ operations that will require different fence configurations.  
  • Construction activities and access will occur within the construction sites.
  • As work areas are complete, more areas of the Common will be opened to the public.


Contact Mitigation

 

Email: mitigation@csl-consulting.com


Call Center Hotline:  (617) 866-8971